What is the End-of-Life schedule for V10 and V11 versions of Commvault software?

Article ID: CS0031 What is the End-of-Life schedule for V10 and V11 versions of Commvault software?

Question

What is the End-of-Life schedule for V10 and V11 versions of Commvault software?

Answer

For V10

Fixes will be supported as follows:

  • Major breakage fixes will be supported until December 15, 2017.
  • Data access fixes will be supported until June 15, 2018.

For V11 

The V11 End-of-Life schedule is by service pack. For each service pack, fixes will be supported as follows:

  • Major breakage fixes will be supported for 9 months from the date of the service pack release.
  • Data Access fixes will be supported for 15 months from the date of the service pack release.

 

Current release and support schedule

Service Pack

Release date

Major breakage fixes will be supported until this date

Data access fixes will be supported until this date

SP8

June 15, 2017

March 15, 2018

September 15, 2018

SP7

March 15, 2017

December 15, 2017

June 15, 2018

SP6

December 15, 2016

September 15, 2017

March 15, 2018

SP5

September 15, 2016

June 15, 2017

December 15, 2017

SP4

June 15, 2016

March 15, 2017

September 15, 2017